Two loads of ties were
picked up from Kitchener Frame who donated them last summer. Thank you
to Lori at
Prestige Acoustics for supplying the
truck and driver.
The first lift of ballast
was placed under the north end of Track 22 and the rail was leveled ready to store #9 and #1518 prior to
the foundation starting. Finish ballasting was completed after the
building was finished.