Construction Photos
March 2010
Notwithstanding the hydro was still not connected, the heat was not working and there was 1.5 feet of frost in the ground the pits were dug. | |||
The hydro was finally connected which will enable us to keep the heat on to eliminate the frost in the floors. | |||
The plumber immediately placing the piping for the pit floor drains and oil separator. | |||
After the plumbing was inspected Integrated Concrete began the construction of the pits. | |||
The finished pits before backfilling. | |||
The balance of the underground plumbing was completed. | ||
The backfilling was completed. | |||
The rail bases were constructed. | |||
Inside the shop the rails were installed by Al and Carson prior to the floors being poured. | |||
Rail material and equipment arrived on site in preparation to install the south approach to the shop. | |||
A drainage system was installed in the south yard by Martin Drainage prior to any rail work starting. | |||