On July 3rd., the excavation of the foundations started by J.R. Fine Grading Ltd. of Kitchener. To facilitate access for the ready mix trucks the north, west and south foundation walls were excavated first.

   

 

 

On July 6th. Able Concrete commenced construction of the the foundation. During the first week the north, west and part of the south wall were poured.

 
On July 11th., the balance of the excavation was completed in the rain.

 

 
Week 2 finishes the east walls of the building's foundation.
   

 

On the 18th of July the completed foundation was backfilled.

 